When the project is complete, the promoter must hand over the common areas — the land, the staircases, the lifts, the corridors, the terrace, the boundary walls, the parks and the common services — to the association of allottees, along with the documents that let the association run them. Common areas handover rera work is where the builder's control of the project actually ends, and it is also where most of the disputes between builders and residents begin.
Two statutes meet at the handover. The Real Estate (Regulation and Development) Act, 2016 defines the common areas in section 2(n) and imposes the promoter's obligations, including the obligation to facilitate the formation of the association; the West Bengal Apartment Ownership Act, 1972 provides the deed of apartment and the declaration by which a building is brought under a common ownership regime. A third layer is the co-operative societies law, where the building is a co-operative housing society.
What counts as a common area
Section 2(n) defines common areas as the entire land and the whole project, including the lobbies, staircases, lifts, common passages, corridors, clubhouse, community and recreational facilities, parks, gardens, common water tanks, sumps, pumps, fire escape stairs and other common facilities, which the promoter retains as common areas for the allottees.
The definition is broad, and it is designed to defeat the practice of carving out the clubhouse, the terrace or the parking from the common areas and selling them separately. Where the agreement for sale promised a clubhouse as a common facility, it is part of the common areas, whatever the builder's internal allocation says.
The obligations at completion
The promoter must complete the project and obtain the occupancy certificate, and must execute the conveyance in favour of the allottees. Section 17 requires the conveyance to be executed within three months of the occupancy certificate, and the Act also requires the promoter to facilitate the formation of an association or society of the allottees.
The handover itself involves more than the keys. The promoter should hand over:
- The as-built drawings, the structural drawings and the approved plans, with the occupancy certificate.
- The completion certificate and the fire no-objection certificate, the lift licence and the electrical safety certificate.
- The maintenance contracts, the warranties for the lift, the pumps and the DG set, and the list of vendors with their contacts.
- The service connection documents for water and electricity, and the meters for the common areas.
- The register of common areas, the corpus fund, and the accounts of the maintenance collected from the date of the first occupation.
- The title documents for the land, and the conveyance in favour of the association.
A handover that omits the drawings and the warranties leaves the association unable to maintain the building, and the cost of reconstructing those documents later falls on the residents.
The association, and the deed of apartment
For a building brought under the West Bengal Apartment Ownership Act, 1972, the owner files a declaration and a deed of apartment, and the apartments become separate properties with defined percentages of undivided interest in the common areas. The association of apartment owners is formed under that Act, and the common areas are held by the owners in those proportions.
For a co-operative society, the land and the building are held by the society, and the members hold shares. For a society registered under the West Bengal Societies Registration Act, 1961, the association holds the common areas as a separate entity. The three structures have different rules for transfer, for maintenance and for the redevelopment decision, and the allottees should know which one they are in before the handover.
Where the handover goes wrong
The first failure is the builder who keeps the common areas in his own name and grants the association a licence to use them. The association then cannot repair, cannot borrow, and cannot resist a sale of the common areas by the builder.
The second is the clubhouse or the parking sold as a separate unit. Where the amenity was promised in the agreement for sale, treating it as a saleable unit contradicts the promise, and the allottees' complaint lies to the Authority.
The third is the maintenance corpus. The builder collects a corpus from each buyer, spends part of it on completing the project, and hands over a bank balance that does not match the collection. The association's first year is then spent on arrears rather than on maintenance.
The fourth is the missing occupancy certificate. Without it the building cannot lawfully be occupied, the conveyance cannot be executed, and the association has no title to the common areas.
The remedy, and the forum
A complaint under section 31 before the West Bengal Real Estate Regulatory Authority can ask for the conveyance, the transfer of the common areas and the documents, and compliance with the promoter's obligations. The Authority can direct compliance, and non-compliance is punishable under the Act.
The association can also proceed in the civil court for the conveyance where the Authority's order is not complied with, and a suit for specific performance of the agreement to convey lies before the City Civil Court at Kolkata or the district court at Alipore or Barasat.
Where the builder has not formed the association at all, the allottees can form one themselves under the applicable statute and then demand the handover in its name. A direction to the promoter to facilitate the formation is part of the Act's scheme, and a complaint that the promoter obstructed the formation is maintainable.
What the association should do on day one
Take possession of the documents against a signed inventory. Open the association's bank account and transfer the corpus. Obtain a valuation of the common assets for insurance. Apply to the municipal assessment department for the common areas' assessment, and to the revenue office for mutation where the land is not yet conveyed. Register the association, and file the annual returns that the statute requires.
Then audit the first year's maintenance with the promoter's accounts, because the transition from the promoter's maintenance to the association's is where money goes missing.
Who owns the car parking?
Where the parking is within the common areas and the agreement does not sell it as a separate unit, it belongs to the allottees collectively, and the association allots it. A builder who sells parking separately after promising it as a common facility is exposed to a complaint, and the position depends on the agreement and the sanctioned plan.
What if the builder refuses to form the association?
The allottees can form the association themselves and complain to the Authority for a direction to the promoter to hand over the common areas and the documents. The Act's obligation to facilitate formation is not discharged by silence.
Does the handover require a registered document?
The conveyance of the land and the common areas requires a registered instrument. The handover of the documents and the maintenance records is a physical transfer against an inventory, and it should be minuted by the association.
Who maintains the building before the handover?
The promoter, from the date of the first occupation until the handover, and the maintenance charges collected for that period must be accounted for. The association should ask for the accounts of that period as part of the handover.
The handover is a documents exercise as much as a legal one, and the association that takes an inventory on day one is the association that avoids a decade of disputes. Our RERA practice acts for associations and allottees on handover complaints, and the property team handles the conveyance and the deed of apartment. Society and trust structures are dealt with through trust registration, and enquiries begin at the contact page.