A RERA complaint west bengal allottee files goes to the West Bengal Real Estate Regulatory Authority constituted under Section 20 of the Real Estate (Regulation and Development) Act, 2016, and it is filed under Section 31. The complaint can ask for possession, for interest for delay, for a refund with interest, for compensation for defects, or for any other relief the Act provides. It is a relatively cheap and quick forum compared with a civil suit, and its usefulness depends almost entirely on the documents annexed to the complaint. Where the allottee is also weighing the consumer commission, the choice should be made before the first filing.
Who can complain, and about what
Section 31 allows an aggrieved person to file a complaint with the Authority or with the adjudicating officer, as the case may be. An aggrieved person includes an allottee, a promoter, and a real estate agent. Most complaints are by allottees against promoters, and the common grounds are these:
- Failure to complete the project or hand over possession by the date in the agreement for sale, which attracts interest under Section 18.
- Failure to give possession of an apartment in accordance with the agreement, and the allottee's right to withdraw and claim a refund with interest.
- Defects in the construction or the workmanship, or a failure to provide the amenities promised, which attract compensation under Section 14.
- Deviation from the sanctioned plan or the specifications, or a change in the common areas without the requisite consent.
- A promoter who has not registered the project, or who has advertised or sold without registration.
- False or misleading advertising, and the failure to disclose the particulars required by the Act.
The Act also binds the promoter to deposit seventy per cent of the amounts realised from allottees in a separate project account, and a complaint about the misuse of that account is within the Authority's jurisdiction.
The form, the fee and the filing
The complaint is filed in the form prescribed by the Authority's regulations, with the project registration number, the unit details, the agreement for sale, the payments made, and a statement of the relief sought. The fee is fixed by the regulations and is modest; the current amount should be confirmed at the Authority's office or on its website, because the schedule is revised.
The filing can be done at the Authority's office in Kolkata, and the Authority has moved much of its correspondence and hearings online. The complaint should be accompanied by an index of documents and a computation of the amount claimed, because a claim for interest that is not calculated is usually sent back for clarification.
The documents that decide the case
- The agreement for sale, with the schedule of payment and the date of possession.
- The allotment letter, the demand letters, and the receipts for every payment, with bank statements showing the transfers.
- The approved plans and specifications, the brochure, and the advertisement that induced the purchase.
- The occupation certificate or completion certificate, where the promoter claims completion, and the possession letter if possession has been offered.
- Correspondence about the delay, the snag list, the promised amenities, and the promoter's responses.
- Photographs of the state of the project or the unit, dated, and a valuation or engineer's report where defects are alleged.
The agreement is the pivot. If the agreement does not fix a possession date, the Act supplies one by deeming the period, and the promoter's own declared completion date in the registration becomes relevant. A complaint that cannot produce the agreement is usually dead on arrival.
What the Authority can order
Under Section 18, where the promoter fails to complete or to give possession as agreed, the allottee may either withdraw from the project and claim a refund of the amounts paid with interest, or continue and claim interest for every month of delay. The interest rate is the one the rules prescribe, and the current rule should be checked, because it is defined by reference to a lending rate and a margin.
Under Section 14, compensation is payable for defects in the construction or the work, and the promoter must rectify the defect within thirty days of a written complaint. Under Section 19, the allottee has a right to obtain the documents of the project and to be informed of the progress, which supports a complaint where information is refused.
An order of the Authority is enforceable as a decree of a civil court under Section 40, and where the promoter fails to comply, the Authority can recover the amount as arrears of land revenue. That is a stronger power than many litigants expect, and it is worth asking for in the complaint.
The timeline and the appeal
The Act requires the Authority to dispose of complaints expeditiously, and the Authority's regulations fix the schedule for replies and hearings. In practice a complaint in Kolkata is listed within a few months, and the promoter's reply, the rejoinder and the arguments occupy further hearings. An order that is complied with is usually the end; an order that is appealed goes to the Real Estate Appellate Tribunal for West Bengal.
An appeal under Section 43 must be filed within sixty days of the order, with a further period of sixty days available at the tribunal's discretion on sufficient cause, and the appeal must be accompanied by the deposit of the amount ordered or the part the tribunal directs. The deposit requirement is a real obstacle for a promoter and a real protection for the allottee.
Mistakes that lose complaints
Filing against the wrong entity is the first: the contracting party is the promoter named in the agreement, which may be a special purpose company rather than the parent developer whose name appears on the brochure. The second is a claim for possession where the allottee has already taken possession, which changes the relief to interest and compensation. The third is a claim for both refund and interest for delay, which are alternatives under Section 18.
The fourth is a complaint without documents. The Authority works on the record, and an allottee who has paid in cash, has no receipts, and cannot produce the agreement has little to show. Payments by cheque or bank transfer, with receipts, are the foundation of every successful complaint.
Common questions
Can I file without a lawyer?
Yes, the Authority's procedure is relatively informal and allottees often appear in person. Representation helps where the computation of interest is disputed or where the promoter raises technical objections about the registration of the project. Our published consultation fee is ₹2,000 for an initial sitting, and the fee for a court or tribunal appearance is separate.
Is there a limitation period?
The Act does not prescribe a specific period for a complaint under Section 31, and the Authority has entertained complaints filed after delay where the reason was explained. A delay of years is still a risk, and the complaint should be filed as soon as the possession date is missed.
Can the promoter deduct anything from the refund?
The promoter is entitled to deduct the amount already paid and to adjust the refund against the dues, but not to impose a penalty for the allottee's lawful withdrawal. Where the agreement contains a forfeiture clause, the Authority examines whether the forfeiture is reasonable and whether the promoter's own default caused the withdrawal.
What if the project is not registered with RERA?
An unregistered project is itself a contravention, and the Authority can proceed against the promoter for the penalty, while the allottee's claim for refund and interest can still be pursued. The absence of registration does not remove the Authority's jurisdiction over a project that should have been registered.
Assemble the agreement, the receipts and the computation before filing, and state one clear relief. Our RERA practice files complaints before the West Bengal Authority and appears in the appeals before the appellate tribunal, and the property team advises on the agreement before the purchase that leads to the complaint.