Section 18 of the Real Estate (Regulation and Development) Act, 2016 gives an allottee a monetary remedy when the promoter fails to complete or hand over the project by the date agreed in the agreement for sale. The allottee may withdraw from the project and claim a refund of the amounts paid with interest, or stay in the project and claim interest for every month of delay until possession. rera section 18 interest delay claims are decided on documents that are usually in the buyer's own file, and they are the most common complaint before the West Bengal Authority.
The arithmetic is not complicated, but the trigger and the rate are, and both come from the statute and the state rules rather than from the builder's payment schedule.
When the right arises
The obligation is to complete and hand over possession by the date specified in the agreement for sale, which must be consistent with the date disclosed at registration. Where the promoter fails to do so, section 18(1) applies. The allottee then has the choice the section gives: withdraw and take a refund with interest, or continue and take interest for the period of delay.
Two qualifications matter. A delay caused by a force majeure event, or by a stay ordered by a court or authority, is excluded to the extent the statute allows; and a delay caused by the allottee's own default in payment gives the promoter a defence, though not for the entire period. The Authority examines the cause of the delay rather than treating every missed date as a violation.
The date in the agreement is the operative date, not the date on which the builder first promised possession in a brochure or at a site visit. Where the agreement was amended to extend the date with the allottee's consent, the extended date governs, which is why a consent to extension should never be signed without advice.
The rate of interest
The Act defines interest by reference to the rate specified in the rules made by the appropriate government. In West Bengal the rate is specified in the state rules, and the same rate applies to the promoter's liability for delay and to the allottee's liability for default in payment, which is the symmetry the statute insists on.
Because the rate is fixed by rule and has been revised, the figure must be taken from the rule in force for the period of delay, not from a number in a newspaper article. The Authority computes interest for the months of delay, on the amounts actually paid by the allottee, and the calculation is usually set out in the order so that it can be checked.
Refund or interest: the choice and its consequences
A withdrawal under section 18(1) entitles the allottee to the refund of the amounts paid with interest, and the promoter must pay within the period the order specifies. Withdrawal ends the contract, so the allottee gives up the flat; that is the trade for the money.
Continuing in the project keeps the flat and gives interest for delay. Where construction is substantially complete and the delay is a matter of months, interest is usually the better route. Where the project has stalled, withdrawal is usually better, because interest on a project that will never be completed only grows the claim while the asset does not.
Whichever route is chosen, the claim is made by a complaint under section 31 to the Authority, which hears it as a consumer-type grievance and passes an order that can be enforced.
Computing the claim
Build a table with the date of each payment, the amount, and the mode. The interest is computed on the amount paid for the period of delay, and a payment made late by the allottee reduces the base or attracts the promoter's own interest claim. Attach the receipts, the bank statements, the agreement for sale, the registration certificate of the project, and the possession date promised.
Where the allottee has taken a loan, the interest paid to the lender is not automatically recoverable under section 18; the statutory interest is the remedy, and the lending cost is relevant to the assessment of compensation only in a case where the Authority is considering the loss suffered.
The forum, and the Kolkata practice
The complaint is filed before the West Bengal Real Estate Regulatory Authority, and for projects in the Kolkata metropolitan area that is the Authority's office in the city. The complaint can be filed online through the Authority's portal, and the fee is prescribed by the rules.
The Authority's order can be appealed to the West Bengal Real Estate Appellate Tribunal within sixty days under section 44, and an appeal does not automatically stay the order; a separate application for stay is needed. The Tribunal's decision can be challenged in the Calcutta High Court on a substantial question of law.
Where the promoter has failed to comply with an order, section 40 provides for the Authority to direct compliance, and non-compliance is a punishable offence. In practice, the enforcement of a refund order is where allottees need help, because an order against a company with no assets is only a piece of paper until it is executed.
What goes wrong
The first failure is a complaint that claims interest from the booking date rather than from the promised possession date. The Authority dismisses the excess and the allottee's credibility suffers.
The second is an allottee who signed an extension letter under pressure at the time of the last demand, and then claims delay for the extended period. The consent defeats the claim for the period it covers.
The third is a claim for refund after the allottee has already taken possession, which converts the dispute into a defects claim under section 14 rather than a delay claim under section 18.
Can I claim both refund and interest?
Yes, under section 18(1) a withdrawal carries the refund of the amounts paid with interest. What you cannot do is take the refund and also keep the flat, because the withdrawal ends the contract.
Is the interest the same rate the builder charges me for late payment?
In principle yes. The Act and the rules use the same rate for the promoter's liability and the allottee's, and a promoter who charges a higher rate for the allottee's default than he pays for his own delay is applying an asymmetrical term that the Authority examines.
What if the delay was because the sanction was held up?
A delay attributable to a court stay or to an event beyond the promoter's control is excluded to that extent, but a delay in obtaining a sanction that the promoter should have obtained before launching the project is not force majeure. The Authority looks at what the promoter could have done.
Can I sell the flat while the complaint is pending?
You can transfer the allottee's rights under section 19 with the promoter's consent and on payment of the statutory transfer fee, and the transferee steps into the complaint. The transfer should be disclosed to the Authority so that the order is passed in the right name.
The claim is built from a payment table, the agreement and the promise of possession, and it succeeds when the arithmetic is right. Our RERA practice files the complaint and the enforcement application, and appeals go through the appellate and writ practice where the Tribunal's order is challenged. Related consumer remedies are covered under consumer protection, and a first consultation can be booked at our contact page.