The Real Estate (Regulation and Development) Act, 2016 does not state a limitation period for a complaint under section 31, and that silence has produced a split in practice. rera complaint limitation is therefore a question about what the Authority does with a stale complaint rather than a question with a statutory answer, and the safe assumption for an allottee is that delay will be raised and will have to be explained.
Different benches have taken different positions. Some have applied the Limitation Act by analogy and dismissed complaints brought after three years from the cause of action; others have held that the Act creates a special remedy with no limitation and that delay goes to the merits. The Supreme Court has not settled the point definitively, and the state rules do not fill the gap.
When the cause of action arises
For a delay in possession, the cause of action arises on the date the promoter failed to hand over possession as promised, and it continues for as long as the failure continues, because every month of delay is a fresh breach for the purpose of the interest claim. That is why a complaint about a project delayed since 2019 can still be maintainable where possession has not been delivered.
For a refund after withdrawal, the cause of action is the date of withdrawal and the promoter's failure to refund. For a false representation, it is the date of the representation and the allottee's reliance on it. For a defect in construction, it is the date the defect was noticed, within the five-year period that section 14 allows.
For a complaint that the project was never registered, the failure is continuing for as long as the project is being marketed without registration, and the breach is the advertising and the booking rather than the completion.
What the Authority does with a late complaint
Where limitation is raised as a preliminary objection, the Authority examines the date of the cause of action and the reasons for the delay. The practice that has emerged is that the Authority is reluctant to dismiss a genuine allottee's complaint on limitation alone where the promoter's breach is continuing, and more willing to do so where the allottee sat on a completed transaction for years.
The complaint should therefore deal with time in its first two paragraphs: state the date of the promise, the date of failure, the correspondence in between, and the date of filing. An allottee who shows that he was writing to the promoter, attending meetings, and waiting for a possession letter has a much better answer than one who produces a booking receipt from 2018 and nothing else.
There is also a practical reason not to wait. The Authority's power to direct a refund is worth what the promoter's balance sheet is worth, and a promoter in difficulty has fewer assets in the third year of a dispute than in the first. Every year of delay reduces the chance that an order, however well founded, is actually satisfied, and that is apart from any question of limitation.
The alternative forums and their periods
Where the RERA complaint is at risk on limitation, the consumer commission is an alternative. Under the Consumer Protection Act, 2019 a complaint must be filed within two years from the date on which the cause of action arose, with condonation on sufficient cause. For a continuing delay, the cause of action is treated as arising on each failure, and the commission's practice on real estate delay is well developed.
A civil suit for specific performance or for damages has its own periods: three years for specific performance from the date fixed for performance or from the date of refusal, and three years for damages. A suit for possession on title has twelve years.
Filing in more than one forum at once is not permitted for the same relief, and an allottee who has already obtained an order from one forum cannot seek the same relief from another. The choice should be made before the first complaint is filed.
Projects that began before the Act
The Act applies to a project that was ongoing on the date of commencement and had not received its completion certificate, and such a project was required to register within the period the rules allowed. An allottee in such a project can complain about the delay, but the delay before the Act came into force is governed by the agreement and the general law, and the Authority's jurisdiction over that earlier period is limited.
Where a project was completed and the occupancy certificate issued before the Act, the Authority has no jurisdiction over the transaction, and the remedy is in the consumer commission or the civil court.
Building the delay explanation
Keep the possession letter, every demand letter from the promoter, the payment receipts, the emails asking for a status, and the minutes of any meeting with the builder. A file that shows a complaint in the first month of delay and a follow-up every quarter answers the limitation objection without an argument about law.
Where the allottee signed an extension of the possession date, the explanation must address it: whether the consent was free, whether it was given in exchange for a concession, and what the promoter promised in return. An extension signed under pressure at the time of the final demand is a different document from a negotiated variation.
Is there a two-year limit for a RERA complaint?
The Act does not prescribe two years. Two years is the consumer commission's period, and it is often confused with RERA because both forums deal with the same transaction. The Authority has applied the Limitation Act's three-year period by analogy in some orders, and has refused to apply it in others.
Does limitation run from the promised possession date?
For a delay claim, yes, and it continues while the delay continues. For a refund claim after withdrawal, it runs from the withdrawal and the failure to refund. For a defect claim, it runs from the defect, subject to the five-year warranty.
Can an old allottee file now?
It depends on whether possession has been delivered and when the breach occurred. Where the flat was delivered years ago and the complaint is about the delay, the Authority may treat the claim as stale; where the project is still incomplete, the breach continues and the complaint is usually entertained.
What if the promoter raises limitation and the Authority accepts it?
The order is appealable to the West Bengal Real Estate Appellate Tribunal within sixty days, and the ground of appeal is that the Authority erred in importing a period the statute does not contain, or in mistaking a continuing breach for a one-time failure.
Time is the first thing the other side will attack, so the complaint should answer it before it is asked. Our RERA practice drafts complaints with the chronology built in, and the consumer practice advises on the alternative forum where the delay is long. Appeals go to the appellate practice, and enquiries begin at our contact page.