Property & Registration

Project foreclosure: a buyer's remedy when the builder stops

When a promoter abandons a project, the Act provides for the revocation of the project's registration and for the project to be completed by the association of allottees or, on their request, by a third party. For the individual buyer, the practical remedies are three: a refund of the amounts paid with interest, a claim in the promoter's insolvency, and participation in the collective effort to have the project completed. Each has a different prospect of recovery, and the choice is usually made on the promoter's balance sheet.

Abandonment is rarely announced. It looks like a site with no workers, a promoter who stops answering, quarterly reports that repeat the same construction stage, and a date of possession that has passed twice.

Revocation of the registration

Section 7 allows the authority to revoke the registration of a project where the promoter defaults in doing anything required by the Act or the rules, where he contravenes the Act or the rules, or where he is involved in any unfair practice. The authority must give the promoter a hearing before revoking.

On revocation, the authority may direct that the project be debarred from being marketed, and it may direct the promoter to return the amounts collected. The revocation is published on the portal, which is how other buyers learn of it.

Revocation is not a remedy that a buyer can obtain quickly. It requires a complaint, an enquiry and a hearing, and the authority may give the promoter time to cure the default. It is worth pursuing when the project is dead, because it stops the promoter from collecting more money from new buyers.

The section 8 procedure

Section 8 applies where the promoter fails to complete the project or is unable to hand over possession, and the registration has been revoked or the project has been foreclosed in the manner the rules provide. The authority may then, on its own or on the request of the allottees, direct that the project be completed by the association of allottees, or by a third party nominated by them.

The section is the statutory foundation for a takeover. In practice it requires an association that is registered, a majority of the allottees behind the proposal, a contractor willing to complete the work, and a funding arrangement. The authority supervises the process and the remaining project is completed under its direction.

That route has been used where the land is unencumbered and the structure is partly built. It rarely works where the land is mortgaged to a lender, because the lender's charge takes priority over the allottees' money.

The refund claim

Section 18 gives the buyer the right to withdraw and claim a refund with interest where the promoter fails to complete or hand over possession. The claim is the simplest remedy, and it is the one to file first if the promoter still has assets.

An order for refund is enforceable, and a failure to comply can lead to recovery as arrears of land revenue and to further penalty on the promoter. Where the promoter is a company with assets, the order has value; where it is a shell, the order is a piece of paper.

The buyer should ask, before filing, whether the promoter owns anything: the land, unsold flats, receivables, a parent company. A refund order against a company with nothing is a waste of the filing fee.

Insolvency, and where the buyer stands

Where the promoter is a company in default, the buyers can initiate or participate in a corporate insolvency resolution process before the NCLT Kolkata bench. Homebuyers are treated as financial creditors where they have paid against a real estate project, and they are represented in the committee of creditors by an authorised representative.

The resolution plan, if one is approved, decides what the buyers receive: completion of the project, a refund at a discount, or a combination. Where no plan is approved, the company goes into liquidation and the buyers' claims are proved in the liquidation, ranking with the other financial creditors in the waterfall.

The advantage of the insolvency route is that it freezes the promoter's dealings, brings the lenders to the table, and produces a collective outcome. The disadvantage is that it takes years, and the outcome is decided by the committee of creditors rather than by the individual buyer.

What "abandonment" looks like in evidence

  • The site is not working, and the photographs over successive months show no change.
  • The quarterly updates stop, or repeat the same stage of construction.
  • The promoter's office is closed, and the phone numbers do not work.
  • The date of possession in the agreement has passed, and no occupation certificate has been applied for.
  • New bookings have stopped, and the project is no longer marketed.
  • The land is mortgaged, and the lender has issued a notice.

That evidence is what a complaint under section 31 or a section 7 application needs. It should be collected as it happens, not reconstructed afterwards.

The civil court, and why it is rarely the answer

A suit for specific performance against the promoter is possible, but it is rarely useful where the promoter has no money and no intention of building. The decree would direct the promoter to complete, and the promoter would not comply.

A suit for a refund, as a money claim, is possible, and it has the advantage of a decree that can be executed against assets wherever they are. It is slower than the RERA complaint, and it is sometimes the better route where the promoter is not registered or the project falls outside the Act.

Coordinating with the other buyers

The individual buyer's leverage is limited; the collective's is not. An association of allottees can negotiate with the authority, approach a completion contractor, and speak to the lender. The first step is usually a WhatsApp group, the second a formal association, and the third a common complaint.

Coordination also prevents the promoter from settling with some buyers and leaving the rest. A common position on the refund figure, or on the completion plan, is stronger than a series of separate settlements.

Kolkata: the forums

The West Bengal Real Estate Regulatory Authority hears the section 31 complaints and the section 7 and 8 proceedings. The Real Estate Appellate Tribunal hears the appeals, the NCLT Kolkata bench handles the insolvency, and the Calcutta High Court hears the writs and the further appeals.

Our RERA practice files the complaint and the revocation application, and the insolvency practice handles the claim before the NCLT. Where the land title itself is in question, the title disputes practice advises on the security available to the buyers.

Can the buyers complete the project themselves?

They can, through the section 8 procedure, if the authority directs it and an association is in place with a contractor and funding. It is done where the land is unencumbered and the construction is well advanced. Where the land is mortgaged or the approvals have lapsed, the practical difficulties are usually too great, and the refund route is more sensible.

What happens to my money if the promoter is insolvent?

It becomes a claim in the insolvency process. As a financial creditor, the buyer is represented in the committee of creditors and receives whatever the resolution plan provides, or a share of the liquidation proceeds. The recovery is usually a fraction of what was paid, and the timing is measured in years.

Is there a deadline for a refund claim?

The Act does not fix one, but the authority applies the law of limitation, and a claim filed long after the promised date can be met with an objection. The practical course is to file within three years of the date of possession promised in the agreement, and to file early where the project has visibly stopped.

A rera project foreclosure is a loss that has to be managed rather than reversed. The buyer who documents the abandonment as it happens, files early, and coordinates with the other allottees recovers more than the buyer who waits for a completion that is not coming.

Looking for a a law firm in Kolkata? FileX Advocates practises from 14 Hare Street, Kolkata 700001, before the Calcutta High Court and the city courts. Consultation ₹2,000.

Book a consultation — ₹2,000 WhatsApp UsAll Articles
Related

More Insights

Guides our advocates wrote on neighbouring questions.

Chat on WhatsApp Call +91-7439811422