A RERA adjudicating officer and the Authority are two distinct decision-makers under the Real Estate (Regulation and Development) Act, 2016, and filing before the wrong one costs months. In broad terms, the adjudicating officer hears claims for interest and compensation under Sections 12, 14, 18 and 19, while the Authority itself hears complaints about registration, penalties and other contraventions and exercises the regulatory powers over promoters and agents. The Act allows a complaint to be filed with either, "as the case may be", which is precisely the phrase that causes the confusion.
How the Act divides the work
Section 71 provides that the Authority may appoint one or more adjudicating officers for the purpose of holding inquiries into complaints and for imposing penalties under the Act. The adjudicating officer holds an inquiry, gives the parties an opportunity of being heard, and passes an order awarding compensation or interest, or imposing a penalty, as the case may be. Section 72 lists the factors the officer must consider while adjudicating: the amount of disproportionate gain or unfair advantage, the amount of loss caused to an allottee or a group of allottees, the repetitive nature of the default, and such other factors as may be specified.
The Authority's own powers are wider. It registers projects and agents, it can revoke a registration, it can direct the promoter to comply with the Act, it can impose penalties for non-registration or for contravention, and it can order the refund of amounts. Under Section 31, a complaint may be filed with the Authority or with the adjudicating officer, and the relief sought usually determines the forum.
The practical allocation
The working distinction adopted by the Authorities, and reflected in their regulations, is this:
- Interest for delay in possession under Section 18, and compensation for defects under Section 14, are claims for money against the promoter and are ordinarily heard by the adjudicating officer.
- Refund of the amount paid with interest on withdrawal is a claim that the Authority hears, because it involves the promoter's obligations under the registration and the project account.
- Penalties for advertising or selling without registration, for failing to deposit the amounts in the project account, or for contravening the Act are imposed by the Authority.
- Registration and revocation of a project or an agent, and directions to comply, are the Authority's regulatory functions and are not adjudicated by the officer.
Where the complaint mixes a refund, interest and a penalty, the Authority may split it or direct the parties to the appropriate forum. A complaint drafted with one clear money claim is easier to place.
Procedure before the adjudicating officer
- File the complaint in the prescribed form with the project registration number, the agreement, the payment records and a computation of the interest or compensation claimed.
- The officer issues notice to the promoter and fixes a date for the reply.
- The promoter files its reply, and the allottee files a rejoinder dealing with the promoter's defences, especially any claim of force majeure or of the allottee's own default.
- The officer hears the parties, may call for the project records, and passes a reasoned order.
- The order is enforceable under Section 40, and an appeal lies to the appellate tribunal under Section 43 within sixty days.
The inquiry is summary in character. The officer is not conducting a full trial, and the documents do most of the work; oral argument is usually confined to the computation and to the promoter's defences.
Computing the claim
Interest for delay is calculated on the amounts paid, from the date of possession fixed in the agreement to the date of actual possession or the date of the order. The rate is the one the rules prescribe; the rules define it by reference to a lending rate and a margin, and the current version should be checked. A complaint that simply asks for "interest as per RERA" without a computation is usually returned for clarification, and a computation that uses the wrong rate invites a reduction.
The officer decides two questions: what was paid, and how late the promoter was. Everything else in the complaint is context.
Where the Authority is the better forum
Where the promoter has not registered the project at all, or has sold units in an unregistered project, the Authority is the forum, because the contravention is regulatory and the penalty is imposed by the Authority. Where the promoter has diverted the project account, or has failed to update the project details on the website, the Authority's directions are the effective remedy, and a money claim to the officer will not produce them.
Where the allottee wants to withdraw and take the money back, the Authority is again the natural forum, because the refund order needs the enforcement machinery under Section 40. A complaint to the officer that asks for a refund rather than compensation may be treated as one for compensation, which is a different remedy with a different computation.
Common questions
Can the adjudicating officer order a refund?
The officer's function is to adjudicate compensation and interest, and the wide refund jurisdiction sits with the Authority. An order of the officer that purports to direct a refund may be challenged as beyond jurisdiction. If the allottee wants the money back, the complaint should be framed for the Authority.
Which forum is faster?
Both sit within the same Authority, and the listing depends on the case load and the nature of the complaint. A pure interest claim before the officer tends to be decided on documents and is often quicker than a regulatory complaint that requires the promoter's compliance record. Neither is a substitute for filing promptly.
Can I file before both?
Filing the same claim before both is not proper, and a second complaint on the same cause of action invites an objection. Where the reliefs are genuinely different, such as a penalty for non-registration and interest for delay, separate proceedings can be maintained, but the complaints should be drafted so that the reliefs do not overlap.
Does the officer's order need to be executed through a court?
The order is enforceable as a decree of a civil court under Section 40, and the Authority can recover the amount as arrears of land revenue. In practice the allottee applies to the Authority for enforcement, and the civil court route is used where the Authority's machinery is slow.
Frame the complaint around one remedy and the forum follows. Interest and compensation go to the adjudicating officer, refunds and regulatory directions go to the Authority, and both are appealable to the tribunal. Our RERA practice drafts complaints for the correct forum and appears before the West Bengal Authority and its appellate tribunal. Where the allottee is also considering the consumer commission, the consumer practice advises on the choice. If the agreement itself has to be read before the complaint is drafted, the property team reviews it.